第六章项目时间管理1. Tocontrol the schedule, a project manager is reanalyzing the project to predictproject duration. She does this by analyzing the sequence of activities withthe least amount of scheduling flexibility. What technique is she using?A. Criticalpath methodB. FlowchartC. PrecedencediagrammingD. Workbreakdown structure1.为了控制进度,项目经理重新分析了项目目的是预测项目的持续时间。她通过分析哪些具有最少量进度灵活性的活动的顺序,她正在用什么技术()?A.关键路径法B.流程图C.前导图法D.WBS
2. Adependency requiring that design be completed before manufacturing can start isan example of a(n):A. Discretionarydependency.B. Externaldependency.C. Mandatorydependency.D. Scopedependency.2.制造之前需要完成设计的依赖关系一个()的例子?A.选择性依赖B.外部依赖C.强制依赖D.范围依赖
3. Whichof the following are GENERALLY illustrated BETTER by bar charts than networkdiagrams?A. LogicalrelationshipsB. CriticalpathsC. Resourcetrade-offsD. Progressor status3.以下哪一项用横道图描述比用网络图要好()?A.逻辑依赖关系B.关键路径C.资源平衡D.进展或状态
4. Ifthe optimistic estimate for an activity is 12 days, and the pessimisticestimate is 18 days, what is the standard deviation of this activity?A. 1B. 1.3C. 6D. 34.如果一个活动的最乐观估计是12天,最悲观估计是18天,这些活动的标准差是多少?()A.1B.1.3C.6D.3
5. Aheuristic is BEST described as a:A. Controltool.B. Schedulingmethod.C. Planningtool.D. Generallyaccepted rule.5.启发法描述为()最合适?A.控制工具B.进度方法C.规划工具D.通用接收准则参考答案:
1.A 2.C 3.D 4.A 5.D
今日思考题(第6章)1. 进度管理计划和进度计划的内容分别是什么,有什么区别?2. 定义活动的目的什么?活动与 WBS的关系是什么?里程碑清单的属性有哪些?3. 排列活动顺序的工具有哪些?PDM中的4种逻辑关系是什么?活动之间的依赖关系有哪些?提前量和滞后量的表示方法,学会根据叙述的信息画出进度网络图。4. 估算活动的资源都包含哪些资源?什么是资源日历?资源日历与资源直方图的区别是什么?估算活动资源的工具有哪些?
2. Adependency requiring that design be completed before manufacturing can start isan example of a(n):A. Discretionarydependency.B. Externaldependency.C. Mandatorydependency.D. Scopedependency.2.制造之前需要完成设计的依赖关系一个()的例子?A.选择性依赖B.外部依赖C.强制依赖D.范围依赖
3. Whichof the following are GENERALLY illustrated BETTER by bar charts than networkdiagrams?A. LogicalrelationshipsB. CriticalpathsC. Resourcetrade-offsD. Progressor status3.以下哪一项用横道图描述比用网络图要好()?A.逻辑依赖关系B.关键路径C.资源平衡D.进展或状态
4. Ifthe optimistic estimate for an activity is 12 days, and the pessimisticestimate is 18 days, what is the standard deviation of this activity?A. 1B. 1.3C. 6D. 34.如果一个活动的最乐观估计是12天,最悲观估计是18天,这些活动的标准差是多少?()A.1B.1.3C.6D.3
5. Aheuristic is BEST described as a:A. Controltool.B. Schedulingmethod.C. Planningtool.D. Generallyaccepted rule.5.启发法描述为()最合适?A.控制工具B.进度方法C.规划工具D.通用接收准则参考答案:
1.A 2.C 3.D 4.A 5.D
今日思考题(第6章)1. 进度管理计划和进度计划的内容分别是什么,有什么区别?2. 定义活动的目的什么?活动与 WBS的关系是什么?里程碑清单的属性有哪些?3. 排列活动顺序的工具有哪些?PDM中的4种逻辑关系是什么?活动之间的依赖关系有哪些?提前量和滞后量的表示方法,学会根据叙述的信息画出进度网络图。4. 估算活动的资源都包含哪些资源?什么是资源日历?资源日历与资源直方图的区别是什么?估算活动资源的工具有哪些?